THIS CONTROLLED DEMO HAS BEEN MOVED TO AUGUST 19TH AT 9 AM . PLEASE CHECK BACK HERE FOR FURTHER UPDATES.

August 8, 2024 – 6pm Update:

BNSF and its contractors plan to conduct a controlled blast at 9:00 a.m. on Monday, August 19th to facilitate removal of the failed bridge span on the South Dakota side of the Big Sioux River at North Sioux City.

 

For public safety, we are asking people within a 1,000-foot perimeter of the site in North Sioux City and Sioux City to remain indoors from 8:30 – 9:15 a.m. on August 19th. The BNSF project team is attempting individual contacts with the affected residents and businesses within the 1,000-foot perimeter.

 

The project team is consulting with various local agencies on a plan to close roads within the perimeter and station several check points to prevent the public from accessing the area during the blasting operations. More detail on road closures within the perimeter will be released as plans are finalized.

 

Following the controlled blast, the blast team will conduct an inspection and provide clearance for the perimeter to reopen to the public. A temporary ring levee has been built to provide protection for the community while the bridge removal work is underway. BNSF has received its permits and will begin work at the site August 9th. Given delays to their schedule, crews are expected to work in double shifts overnight this Friday and Saturday, August 9th and 10th, and possibly Sunday, August 11th.

 

The planned timeline of the operations is below. For questions regarding the blasting operations, contact Amy McBeth, BNSF Public Affairs, at amy.mcbeth@bnsf.com or 763-782-3212.

 

 

August 19, 2024

8:45 a.m.            Check points are established and roads closed within the 1,000-foot perimeter in North Sioux City and Sioux City

 

8:55 a.m.            All personnel are in safe locations and public is out of perimeter. Five-minute warning siren sounds

 

8:59 a.m.            One-minute warning siren sounds. “All Clear” check from all check points confirmed

 

9:00 a.m.            If “All Clear” then 10-second count down to the blast

 

9:05–9:15 a.m. Blasters conduct post-blast inspection

 

9:15 a.m.            If the “All Clear” has been given from post-blast inspection, the perimeter is reopened to the public.